SAN FERNANDO CATHEDRAL 1975, 1976, 1988, 1998, 1999 2000 San Antonio, Texas
Scope: Manuel F. Lizcano was the mechanical -electrical engineer for the Restoration & Renovation of the 19th Century Nave in 1975, the Restoration and Renovation of the 18th Century Sanctuary in 1976, the and the Priest Quarters in 1976 with Ford, Powell and Carson Architects. The Addition to the San Fernando Rectory with Morkovsky + Associates in 1988 and again with Ford Powell and Carson in 1998 in a systems assessment report. In 1999 we are the ME team member for Rafferty Rafferty Tollefson Architects, Fisher Heck Architects and Sprinkle Robey Architects in a Master Plan Project for San Fernando Cathedral Historic Restoration & Expansion. This master plan The Cathedral Historic Restoration, The Cathedral Centre and the Cathedral Community Centre. Construction Documents for the Cathedral Historic Restoration, and The Cathedral Centre were prepared by Rafferty Rafferty Tollefson Architects and Fisher Heck Architects with Lizcano Consulting Engineers as Mechanical – Electrical Consultants.
CONSERVATION ENVIRONMENT PROJECT (Phase I)
McNayArt Museum San Antonio, Texas Project Cost: $2,500,000 Scope: Construction of Central Chilled and Hot Water Plant. Distribution system for 7 building systems (40,000 sq. ft.) including replacement of existing units. Equipment and controls to maintain temperature and humidity, new humidification system, new gaseous and particulate filtration, DDC controls Fire Protection and new lighting system for the Main House
MASTER PLAN FOR MECHANICAL AND ELECTRICAL SYSTEMSMcNayArt Museum
San Antonio, Texas Project Cost: $5, 033,000 estimated probable cost) Scope: Research, investigations, evaluation and development of options for the recommendation of a consistent, stable and quality environmental control system for the McNay Art Museum. Evaluation of options for Central Plant and development of schematic design to develop accurate construction estimates. 82,000sq.ft with expansion to 150,000 sq.ft
Canadian, Texas Scope: Restoration of 1950’s movie theater. WEBB COUNTY COURTHOUSE Laredo, Texas Scope: Adaptive reuse.
SOUTHSIDEINDEPENDENTSCHOOL DISTRICT
San Antonio, Texas Project Cost: Estimated: $13,000,000 Scope: 286,540 sq.ft.-two story Pre-cast wall construction Administration, classrooms, science labs, trades, cafetorium competition gym and girl's gym. Services Provided: ACHV and Electrical
McNayArt Museum
San Antonio, Texas Scope: Various service provide for the McNayArt Museum through the years include: The Stieren Addition, The Tobin Library, The Frost Galleries, Lawson Addition, and various minor projects such as water pump for the water tower and the pumping system for the main decorative fountain.
CONTINUING EDUCATIONCENTER
TrinityUniversity San Antonio, Texas Project Cost: $535,000 Scope: Adaptive re-use of historical structure Offices and classrooms Services Provided: Plumbing, ACHV & Electrical
SHAVANOPARKCITY HALL AND POLICEBUILDING
City of Shavano Park Shavano Park, Texas Project Cost: $1,400,000 Scope: HVAC, Plumbing, Lighting and Power design and construction documents. Design includes multiple DX rooftop units, and backup power generation for police station. The 11,000SF facility includes three (3) inmate cells designed to State of Texas Jail Standards.
HENRY A. GURREA, JR BRANCH LIBRARY
San Antonio Public Library San Antonio, Texas Project Cost: $1,768,000 Scope: 18,000 Square Foot library Buildings. Split System DX/hot water heating system, for library, offices, and conference rooms. Services Provided: Construction Documents and construction Administration for mechanical and electrical work.
HARRISMIDDLE SCHOOL
San AntonioIndependentSchool District Project Cost: $578,808.00 Scope: 72,000 Square Feet including portable Buildings. Retro Fit chilled/hot water 260 ton central plant, air conditioning system, new primary electrical and conversion to 480/277-208/120 Volt system. Services Provided: Construction Documents and construction Administration for mechanical and electrical work.
SOUTHSIDEINDEPENDENTSCHOOL DISTRICT
San Antonio, Texas Project Cost: Estimated: $13,000,000 Scope: 286,540 sq.ft.-two story Pre-cast wall construction Administration, classrooms, science labs, trades, cafetorium competition gym and girl's gym. Services Provided: ACHV and Electrical
SAMSCOBUILDING
San Antonio, Texas Project Cost: $ 3,033,000 Scope: Renovation Project: Plumbing, Air Conditioning, Heating and Ventilation, for 115,000 sq. ft. of offices for state agencies.
FLOW EQUALIZATION FACILITIES
Dos Rios/Leon/Salado Wastewater Treatment Plants City of San Antonio Project Cost: $800,000 (Electrical Construction Only) Scope: One 30 and two 12 million gallon facilities consisting of diversion structures, diversion pump station, bar screens, pre-aeration basins, parshall fumes, second diversion structures, return pump stations and equalization basins. Services Provided: Design of all electrical and instrumentation systems.
DIGESTER REHABILITATION
Leon Creek & Salado Creek Wastewater Treatment Plants City of San Antonio Scope: New sludge lines and automatic valves for each digester, replacement of heaters with larger boilers, addition of water heating systems, addition of mixers, addition of waste gas burners, construction of motor control building, installation of new electrical work, and installation of related piping, mechanical and instrumentation work. Services Provided: Construction Observation for electrical and instrumentation work.
FIRE STATION NO. 15
City of San Antonio Project Cost: $644,000 Scope: 3800 square feet; four pump truck station; 15 ton AC system. Services Provided: Construction Documents and construction Administration for mechanical and electrical work.
LAREDOJOBCORPSCENTER
U. S. Department of Labor Employment and Training Administration Services Provided: Site survey of mechanical and electrical systems. Construction Documents of Mechanical & Electrical work
CAPEHART HOUSING UNITS
Replace HVAC Systems for 123 Existing Units Lackland AFB: (Department of the Army Corps of Engineers) Project Cost: $780,000 Services Provided: Construction Documents for mechanical and electrical work
LOADING DOCK, ADDITION
Building 360 Kelly AFB: (San Antonio Real P-Property Maintenance Association) Services Provided: Construction Documents for extension of chilled and hot water systems, plumbing fire protection sprinkler system and electrical system.
FAMILYSERVICECENTER
Naval Air Station Kinqsville, Texas Services Provided: Construction Documents for Air Conditioning, Heating Ventilation Plumbing, Lighting and Power for new facility
SOUTHWEST RESEARCH LAB
Alterations to Fuel & Lubrications Lab San Antonio, Texas Southwest Research Laboratory (Department of the army, Forth Worth District Corps of Engineers) Services Provided: Replace and upgrade engine exhaust system, Replace existing HVAC: system.
FOX PHOTO PLANT
Dallas, Texas Project Cost: Estimated: $795,000 Scope: 16,500 sq.ft.-two story existing building Photo processing plant, administration, receiving, dark rooms, films processing, cut & sort chemical storage. Services Provide: Preliminary Scheme: All new systems: New systems supplemental with existing system: existing system supplemented new systems. Final design of selected schemes Plumbing. ACHV & Electrical
U.S. ARMY RESEARCH LABORATORY
SouthWestResearchCenter
San Antonio, Texas
Project Cost:$204,300
PARKING STRUCTURE: INTERNATIONALAIRPORT
San Antonio, Texas
Project Cost:$7,500,000
Scope: Fire Protection, domestic water, heating & ventilation systems for 500,000 sq. ft., 3 level garage with 1300 car capacity.
BEXARCOUNTYADMINISTRATIONBUILDING
Bexar County, Texas
Project Cost: $7,200,000
Scope: Plumbing, Fire Protection, Air Conditioning, Heating, Ventilation, and Electrical for 100,000 sq. ft. of office structure and 180,000 sq. ft. of parking structure.
MIDLAND EXHIBITION HALL
Midland, Texas
Project Cost: $317,000
Scope: Pluming, Sprinkler, Air Conditioning, Heating, Ventilation, and Electrical for 12,600 sq. ft. of multi-purpose facility.
THE BLUMBUILDING
Galveston, Texas
Project Cost:$600,000
Scope: 30,000 sq ft. three story 19th Century iron clad structure. Adaptive reuse: Victorian-style restaurant on first level and offices on upper levels.
Services provided: Plumbing, HVAC: & Electrical
THE SELWYN LIBRARY, MUSIC, DRAMABUILDINGS
Denton, Texas
Project Cost:$450,000
Scope: 17,300 sq. ft.
Services provided: Plumbing, HVAC and Electrical complete through construction documents rents
URSULINEACADEMY
San Antonio, Texas
Adaptive reuse by Southwest Craft center
Project Cost: $400,000
Scope: Project One: Basement of existing dormitory - adaptive reuse
Project Two: Chapel - adaptive reuse - conversion to assembly area and meeting rooms while maintaining historical integrity
Services provided: Plumbing, HVAC & Electrical
WILLLAM WALDO CAMERON
Waco, Texas
Project Cost: $300,000
Scope: Three-level Mediterranean style mansion renovated as the home of the WacoCreativeArtCenter
Services provided:Plumbing, HVAC & Electrical
DATAPOINTBUILDING, NO. 4
San Antonio, Texas
Project Cost: $1,452,000
Scope: 144,800 sq. ft. electronic assembly area and paint spray booths
Services provided:Plumbing, HVAC & Electrical
UNIVERSITY OF DALLAS:UNIVERSITYCENTER
Irving, Texas
Project Cost: $1 516,000
Scope:New 3 story addition - 30,200 sq. ft.: Dining, kitchen, rathskeller, dining and kitchen gallery, party rooms, -and kitchen, maintenance and operation dock. Remodel existing 2 stories - 19,000 sq. ft.: Recreation, bookstore, post office, gallery, deans offices, managers apt. student publications office, meeting room, clinic.
Services provided:Plumbing, HVAC & electrical
LA QUINTA MOTOR INN
Lubbock, Texas
Project Cost:$657,280
Scope:104 unit 2 story motel; laundry with 3 commercial washers and dryers; heated pool.
Services provided: Plumbing, HVAC: & Electrical
STORE & WAREHOUSE BUILDINGS A.C. TOUDOUZE
San Antonio, Texas
Project Cost:$90,000
Scope: 48,000 sq.ft. Warehouse; 2 story store area; 1st floor 32,000 sq. ft. sales area and customer office and T/R; 2nd floor 26.800 sq. ft. sales area and an administration offices, T/R and lunch room.
Services provided: Plumbing, HVAC & Electrical
PARK TEN OFFICE GARDEN COMPLEX
San Antonio, Texas
Project Cost: $2,100,000
Scope: Six - 2 story office buildings on landscape site 2 - 33,180 sq. ft. buildings (a) 120T each 282 KW. 2 - 18,540 sq. ft. buildings (b) 80T each 213 KW ea.
WATERGATE APARTMENTS
Little Rock. Arkansas
Project Cost: $1,900,000
Scope: 19 buildings:5-4 apt. buildings; 12-8 apt. buildings; 2-12 apt. buildings; total of 140 apartments. Club; Managers office, club area, maintenance and laundry. Pool: Heated pool adjacent to club.
Services provided: Plumbing, HVAC & Electrical
J.C. PENNY'S STORE NO. 1339
Joplin, Missouri
Project Cost:$ 2,000,000
Scope: Main store: 1st floor - sales areas, display windows, stock areas, toilet roans, dressing rooms, beauty salon, total area 1st floor, 61,400 sq. ft. 2nd floor - office area, work and stock area; 20,160 sq. ft. Mechanical room:4,600 sq.ft. Future sales area:36,640 sq. ft. tba store: (tires, batteries and accessories) - sales, office and lunch and T/R area - 3800 sq. ft. Service (12 overhead doors) - 4400 sq. ft. Storage area - (2 levels at 1660 sq. ft.) 3300 sq. ft.Total area = 11,500 sq. ft.
Services provided:Plumbing & HVAC, Electrical distribution and electrical specifications.
KLEBERGBANK & OFFICEBUILDING
Kingsville, Texas
Project Cost: $1,400,000
Scope:3 story office building with basement - total 52,00 sq. ft.
Services provided: Plumbing and complete charge of construction phase.
SAN ANTONIO SAVINGS & LOAN ASSOCIATION
San Antonio, Texas
Project Cost: $2,000,000
Scope: 13 story office building
Services provided: Drafting and minor design of Plumbing & HVAC systems.
BEXARCOUNTYCOURTSBUILDING
San Antonio, Texas
Project Cost:$12,000,000 (estimated)
Scope: 13 story structure and basement concourse (future adjacent 13 story tower). Basement: sheriff's offices, mechanical equipment ~d First floor: Meeting rooms. 2nd floor: Offices of criminal District Atty., audit probation offices. 3rd floor: Central filing, -mental health offices. 4th floor: J.P. Courts; constables; district courts. 5th thru 13th floors: 28 court rooms; future courts
Services provided: HVAC preliminary design
NAVAL AIR STATION
Corpus Christi, Texas
Project Cost: $786,000
Scope:Control tower: 5 story structure surmounted by octagonal control cab. 2532 sq. ft. communication equipment floor, and back-up equipment floors, mechanical equipment floor, elevator equipment floor. RATCC Building: 1 story structure, 6600 sq. ft. - operations roan, communications equipment room, offices, training room, men and women locker and T/R, telephone roan, recorder, Mechanical, roan, generator roam.
Services provided: Plumbing and HVAC
OFFICERS QUARTERS:BROOKS AIR FORCE BASE
San Antonio, Texas
Project Cost: $600,000
Scope: Building A - 7060 sq. ft. ea. of two floors, Building B - 6728 sq. ft. ea. of two floors
Building C - 6728 sq. ft. ea. of two floors
Services provided: HVAC: and primary electrical distribution
AMERICAN NURSING & CONVALESCING HOME
San Antonio, Texas
Project Cost:$886,150
Scope: 2 level center for 100 patients: lower level - 18,800
Sq. ft., upper level - 26,000 sq. ft. administration, central
nurses station, personal dining, dining and assembly, library,
TV and conversation, commercial kitchen, mechanical roan, men
and women’s lockers, commercial laundry, therapy clinic, toilet
-rooms. Each of four wings consists of private, double and qua-
duplex units with a nurses station, tub and shower area.
Services provided: Plumbing and HVAC and complete charge of construction phase.
ELECTRONIC OVERHAUL DEPOT:
KELLY AFB, BUILDING
308 San Antonio, Texas
Project Cost: $350,000
Scope:Standard clean room, controlled area room, air locks, parts clean room, & offices: 19,775 sq. ft.
Services provided:Drafting of ductwork, piping diagram, schedules and plumbing systems. Design of plumbing systems. Sizing of air distribution system.